Bloom Energy Falls 8.7% as Oracle Force Majeure Notice Revives Project Jupiter Concerns

Bloomberg··USCN·Read original
4▲0 ▼4Impact / 5
Summary · why it matters

Bloom Energy shares fell 8.7% in the afternoon session after Oracle sent a force majeure notice to a Blue Owl Capital unit developing Project Jupiter, the New Mexico AI data center campus designed to run on Bloom's solid oxide fuel cells, seeking to defer rent if the site misses its 2028 target. Oracle and Blue Owl both said the project remains on schedule and that financial commitments are unchanged, but Bloomberg reported that roughly $18 billion of construction loans tied to the campus were already trading below 90 cents on the dollar, signaling lender stress. The lead-plaintiff deadline also arrived Monday in a securities class action over Bloom's disclosures on Chinese-sourced scandium oxide. The move came as Morningstar, citing Dow Jones, reported the 10-year Treasury yield climbing to 5.218% and technology shares leading early declines, a backdrop that tends to punish high-duration growth names tied to long-dated AI infrastructure cash flows. Bloom Energy is up 169% since the beginning of the year, but at $265.44 per share it is still trading 23.2% below its 52-week high of $345.85 from June 2026.

Impact on assets 8

Financials▼ · 3 stocks
Blue Owl Capital Corporation
OBDC
▼ NegativeCapitalrelevance

Blue Owl unit developing Project Jupiter received Oracle's force majeure notice, and ~$18B of construction loans tied to the campus trade below 90 cents, signaling lender stress.

Blue Owl Capital Inc
OWL
▼ NegativeCapitalrelevance

Blue Owl Capital's unit developing Project Jupiter faces Oracle's force majeure notice and stressed construction loans tied to the campus.

Energy Transition & Power Demand▼ · 2 stocks
Bloom Energy Corp
BE
▼ NegativeDemandRegulationrelevance

Oracle's force majeure notice on the Project Jupiter data center campus threatens the fuel-cell project that is a key demand driver for Bloom.

Cloud & Digital Infrastructure▼ · 1 stocks
Oracle Corporation
ORCL
▼ NegativeCapitalrelevance

Oracle sent the force majeure notice seeking to defer rent on Project Jupiter, and its related construction loans are trading below par.

Communication Services▲ · 1 stocks
Others▲ · 1 stocks